Contracts for Difference (CfD) deadline extensions Europe · 9h ago

LCCC Extends Dogger Bank A CfD Deadline by Eight Months to July 2027 as Turbine Repairs Continue in UK

LCCC grants Dogger Bank A offshore wind farm an eight-month CfD delay to July 2027 amid GE Vernova turbine repairs and commissioning setbacks in the UK.

RD

Research Desk

23 October 2026 · 2 min read

The Low Carbon Contracts Company (LCCC) has approved a revised Contracts for Difference (CfD) start date of 31 July 2027 for the first 300 MW tranche of the 1.2 GW Dogger Bank A offshore wind farm in the UK.

The new deadline, which applies to the contract awarded under Allocation Round 3 (AR3), replaces the previous contractual deadline of 30 November 2026 and represents an eight-month extension.

Dogger Bank A CfD Activation Deadline Extended

SSE, Equinor, and Vårgrønn, the developers behind the project, are understood to have advised LCCC that Dogger Bank A would be unable to meet the commissioning milestones and minimum generating capacity requirements needed to activate the contract by the original deadline.

The extension concerns the contractual requirements for bringing the first 300 MW CfD tranche into effect and does not represent a new target for the wind farm's first electricity generation. Turbine repairs and commissioning work continue in parallel.

2024 Blade Failures Prompt Wider Inspection Programme

The revised schedule follows construction difficulties in 2024, including two blade failures involving GE Vernova Haliade-X turbines. Blade damage incidents occurred in May and August 2024.

Following the August incident, the project team reported that GE Vernova's investigation had linked the failure to conditions encountered during turbine commissioning. The incidents prompted further inspections across the wind farm, which identified additional repair requirements.

More than ten turbines are understood to require replacement blades and work on certain nacelle components. The two turbines affected by the earlier blade failures are also expected to receive replacement towers, nacelles, and blades.

These repairs have added to the commissioning workload at Dogger Bank A, which was originally scheduled for completion in 2024.

Developers Point to Known Delays

A project spokesperson attributed the CfD extension to the continuing effects of the 2024 construction setbacks and their impact on commissioning. The developers indicated that the revised timetable was consistent with delays previously communicated to the market.

The commissioning difficulties described have affected Dogger Bank A only.

Operational Outlook and Remaining Tranches

The 95-turbine Dogger Bank A project, located approximately 130 km off the UK coast, is now expected to become fully operational in the third quarter of 2027, according to the latest SSE energy market disclosure cited in the report.

Despite the extended timetable, the developers maintain that the wind farm will be substantially available for electricity generation by the end of 2026. The extension applies only to the first 300 MW CfD tranche.

No changes have been reported for the remaining two contract tranches, which retain their existing long-stop dates of 31 January and 31 May 2027, respectively.

On the record

Category

Contracts for Difference (CfD) deadline extensions

Region

Europe

Industry

Power

Published

23 October 2026

Length

2 min read

Tagged

Dogger BankContracts for Difference (CfD)Offshore WindGE Vernova Haliade-X

Live from the tracker

The projects behind these stories

Capacity, capex, stage, contractors and verified contacts for every project we track, updated daily.

View the project tracker
SVEA/IB - Sylen Offshore Wind Power Plant 8675 MW · Sweden · 8,675 MW · Planning GN - IJmuiden Ver Offshore Wind Power Plant Program 6000 MW · Netherlands · 6,000 MW · Planning APE/SEG/TG - Can Gio Offshore Wind Power Plant 6000 MW · Vietnam · 6,000 MW · Announced GV - Can Gio 2 Offshore Wind Power Plant Program 6000 MW · Vietnam · 6,000 MW · Planning SU - Raahe Offshore Wind Power Plant Zone 6000 MW · Finland · 6,000 MW · Planning CIP/FLS/LFE - Aland Energy Island Offshore Wind Power Plant 6000 MW · Finland · 6,000 MW · Planning SBVP - Farol Wind Power Offshore Wind Power Plant 5700 MW · Santa Catarina, Brazil · 5 MW · Planning Shizen - Projeto Rio Grande do Sul Offshore Wind Power Plant 12000 MW · Rio Grande do Sul, Brazil · 12,000 MW · Announced SBVP - Marine Vortice WOS Offshore Wind Power Plant 5220 MW · Rio Grande do Sul, Brazil · 5,220 MW · Planning GEW - Gavle Ost Offshore Wind Power Plant 4860 MW · Sweden · 4,860 MW · Planning SVEA/IB - Sylen Offshore Wind Power Plant 8675 MW · Sweden · 8,675 MW · Planning GN - IJmuiden Ver Offshore Wind Power Plant Program 6000 MW · Netherlands · 6,000 MW · Planning APE/SEG/TG - Can Gio Offshore Wind Power Plant 6000 MW · Vietnam · 6,000 MW · Announced GV - Can Gio 2 Offshore Wind Power Plant Program 6000 MW · Vietnam · 6,000 MW · Planning SU - Raahe Offshore Wind Power Plant Zone 6000 MW · Finland · 6,000 MW · Planning CIP/FLS/LFE - Aland Energy Island Offshore Wind Power Plant 6000 MW · Finland · 6,000 MW · Planning SBVP - Farol Wind Power Offshore Wind Power Plant 5700 MW · Santa Catarina, Brazil · 5 MW · Planning Shizen - Projeto Rio Grande do Sul Offshore Wind Power Plant 12000 MW · Rio Grande do Sul, Brazil · 12,000 MW · Announced SBVP - Marine Vortice WOS Offshore Wind Power Plant 5220 MW · Rio Grande do Sul, Brazil · 5,220 MW · Planning GEW - Gavle Ost Offshore Wind Power Plant 4860 MW · Sweden · 4,860 MW · Planning