Ocean Winds Completes Turbine Installation at 500 MW Dieppe-Le Treport Wind Farm
Ocean Winds completes turbine installation at the 500 MW Dieppe-Le Tréport offshore wind farm, with full power and commissioning expected within weeks.
Research Desk
Ocean Winds has finished installing all 62 turbines at its 500 MW Dieppe-Le Tréport offshore wind farm (EMDT) off the Normandy coast, the company announced on 27 November 2026. The installation campaign, which Ocean Winds said lasted around six months after starting in June 2026, saw the turbines mounted on jacket foundations. Full power is expected within weeks as commissioning continues.
Power Production Underway Since Summer
The wind farm has been feeding renewable electricity into the grid progressively since first power in July 2026, with turbines connected and electrified as installation advanced.
With the final machine now in place, the remaining work centres on commissioning. According to Ocean Winds, once operating at full capacity the project will generate renewable electricity equivalent to the annual consumption of approximately 850,000 people. Ocean Winds described the completion of the turbine campaign as the safe and coordinated delivery of a complex offshore construction programme.
Company Sees Long-Term Role in French Market
Marc Hirt, Country Manager for France at Ocean Winds, said the installation milestone is significant both for the project and for the company's position in France. He said it demonstrates the company's capacity to deliver complex offshore wind projects and brings the wind farm another step closer to full operation.
Hirt said Ocean Winds, which is jointly owned by EDP Renewables and ENGIE, operates as a long-term owner-operator and is committed to continuing to grow its activities in France.
He said this would contribute to the country's energy transition and to independence, sovereignty and job creation. That owner-operator role will continue at Dieppe-Le Tréport as the wind farm moves from construction and commissioning into operation.
Project Director Cites Decade of Development
Frédéric Flaus, Project Director at Éoliennes en Mer Dieppe-Le Tréport, said the installation of the last turbine closes out more than ten years of development, consultation and collective effort.
He noted that it follows several years of offshore works, which he attributed to the commitment and professionalism of all the project teams and partners. Flaus said that with 62 turbines and 500 MW of installed capacity, the wind farm will support France's energy transition and energy independence over the long term, along with the economic vitality of the region. He said he was very proud of the collective achievement and of the legacy the project will leave for Normandy and its residents.
Dialogue With Maritime Stakeholders to Continue
Flaus also addressed the project's relationship with local stakeholders, saying the wind farm has been built through dialogue with the territory. That dialogue, he said, will continue to support long-term coexistence with other maritime activities, notably fishing.
Industrial and Employment Footprint in Normandy
According to Ocean Winds, the project represents a long-term industrial and economic presence in Normandy. The company said construction mobilised 3,500 full-time equivalent jobs and generated more than USD 197.35 million in activity for small and medium-sized enterprises. The operations and maintenance base in Dieppe was built entirely by local companies, Ocean Winds said. Over the wind farm's 25-year operational period, the base will support 70 full-time jobs.
Commissioning Continues Ahead of Full Output
With all 62 turbines installed on their jacket foundations, Ocean Winds said commissioning is continuing and the wind farm is expected to reach full power over the coming weeks. Until then, the turbines already connected and electrified will keep supplying renewable electricity, as they have done progressively since July 2026.
On the record
Project Completion
Europe
Power
3 min read
Tagged
Also read
DNV Grants Design Compliance Statement for Synera's 495 MW Formosa 4 Project
Ørsted and Skyborn Bring 704 MW Revolution Wind Farm Fully Online With 65 Turbines Off Rhode Island, US
Vestas and Van Oord Complete 52-Turbine Installation at Ecowende's 760 MW Wind Farm in Netherlands
Live from the tracker
The projects behind these stories
Capacity, capex, stage, contractors and verified contacts for every project we track, updated daily.